Start Date: 2017
Completion Date: 2019

Vineyard Wind Connector (Barnstable)

Project Applicant: Vineyard Wind LLC 
Project Location: Town of Barnstable, with offshore export cable landing at Covell’s Beach and onshore export cable terminus at existing substation in Independence Park, Hyannis 
Project Description: Construction and operation of the portion of the Vineyard Wind Connector Project located within Barnstable County, which Project is intended to connect to and serve the proposed approximately 800 megawatt Vineyard Wind offshore wind project; offshore export cables located within Barnstable County waters, the onshore duct bank and associated onshore export cables within existing rights of way, and the proposed onshore substation. 


Physical application files are available for review at the Cape Cod Commission Office Monday-Friday from 8 a.m. to 4:30 p.m. Contact the Front Desk for more information, 508-362-3828.

Project Resources

View All Resources

18M pdf
Oct 29, 2024
2021-09-17 VW1 MM1 Final Plans
Stormwater Pollution Prevention Plan Template Stormwater Pollution Prevention Plan Template on Iin AN ABB & SNC LAVALIN COMPANY o o Independence Drive on Iin AN ABB & SNC LAVALIN…
14M pdf
Jun 04, 2021
2021-06-01 VW1 MM1 Addl Materials
1 Jeff Ribeiro From: Elizabeth Hansel Sent: Tuesday, June 1, 2021 10:42 AM To: Jeff Ribeiro Cc: Tricia Foster; Ted Barten Subject: RE: Vineyard Wind 1…